Construction Update

Works are progressing rapidly on-site. In a recent major milestone, construction of suspended slabs have started and a Tower Crane is now on-site and operating. Bulk and detail excavation works are 100% complete.

Waterproofing to blockwork basement retention works northern, eastern, and western portions of the site and to the lift overrun pit are 100% complete. Slab on Ground is close to completion and the first precast vertical elements were installed on 14 January 2008.